Shropshire Union Canal Society
Work party report: 1–4 October 2026

Kind weather and strong volunteer numbers helped Shropshire Union Canal Society make outstanding progress across several areas during its October restoration work party.

Activity spanned more than half a kilometre of channel, with volunteers tackling tree felling, vegetation clearance, wash wall construction, channel lining, bund construction, concrete chute modifications and wildflower seed sowing.

Restoration project manager Tom Fulda said: “With the high volunteer numbers that have now become something of a norm, it is not unusual to report progress on multiple fronts. The October work party felt particularly varied.

“A preparation day before the main Friday start helped us make the most of the strong turnout. Once again, we were joined on Friday by five volunteers from local business Aico, who seemed to enjoy themselves. We are grateful for their support.”

The main priorities were to complete the channel in Phase 2, finish laying the wash wall blocks through Schoolhouse Bridge and fell the remaining trees in the Phase 3 channel. All three objectives were achieved, with volunteers also completing several additional tasks.

In Phase 2, the final lengths of permanent liner and the channel bed blocks had been laid during the previous work party. This time, volunteers completed the more intricate finishing work, laying blocks up the sides, manually placing riprap and soil covering, and constructing and covering a temporary bund.

The bund will mark the temporary end of Phase 2 until the sections through Schoolhouse Bridge to Malthouse Bridge are completed and connected. Phase 2 is due to be rewatered over winter, ready for water testing next year. As the bund is temporary, its liners have been pegged around the top and do not require a full covering of blocks.

Work on the wash wall began on Friday with the placement and compaction of backfill behind the half-height wall built during the previous work party. A further three courses of blocks were laid between Saturday and Sunday morning, before the ground level on the channel side was raised.

This will allow the concrete pour planned for the following week to be carried out using power barrows instead of pumping, providing a considerable cost saving. Much of the material placed in the channel will subsequently be used as backfill behind the newly completed courses. Coping stones will then be added and the towpath reinstated.

Progress in Phase 3 was particularly impressive. Volunteers burned substantial quantities of brash left from the previous work party on Thursday, clearing the site ahead of tree felling.

The felled material was separated into brash for burning and firewood, with plenty available for volunteers and local residents.

With the main clearance work complete, attention turned to the many remaining tree stumps. Work began on Saturday and, by Sunday afternoon, all but one particularly large stump had been removed. Volunteers also made a good start on burning the removed stumps.

The work has transformed the site, while several trees above water level have been retained on the offside bank. Further progress in Phase 3 this year will depend on the weather, as this section typically becomes wet over winter.

On Sunday, some volunteers also ventured into Waen Wen to remove willow shoots that had appeared since last year’s felling. The task proved particularly popular with some members of the team.

Overall, it was an exceptionally productive work party, with a wide variety of tasks offering something for everyone.